Moraine Avenue Bridge Upgrades

APRIL CLOSURE OF ELKHORN

In April, Elkhorn Avenue will be closed for needed utility work. The closure of the intersection will begin the evening of April 8 and continue until April 30, weather permitting. If at all possible, the work will be completed sooner and the road reopened before April 30. View the presentationMap of closure area and pedestrian detours.


April 13, 2018

The construction contractor completed the pour of the top slab of the box culvert this week. Following delays with rebar and post-tensioning work, weather and concrete delivery, this was a welcome accomplishment. In the coming week work will take place on the wing walls and head walls and tensioning will occur.

Utility Update: Estes Park Sanitation District completed their installation of the sanitation line across Elkhorn Avenue this week. They will transition toward the Moraine Avenue Bridge. Global Underground, subcontractor, is installing the water line, crossing the Elkhorn Avenue intersection by the end of the week.

April 5, 2018

In order to replace a valve for necessary tie-ins of new water lines, the Water Division must schedule a water outage for properties on a portion of Moraine Avenue, from the public restrooms at the Weist Parking Lot north to Rockwell Avenue from approximately 9 a.m. until 12 p.m., Friday, April 6, 2018. Affected properties were notified by staff and door hangers April 5.


Detour and parking map (detour applies for the project duration except during the April closure at the Elkhorn Avenue intersection with Moraine Avenue):Parking -Detour Map.jpg