CDOT US 85 Construction Schedule for June

3-Week Look Ahead Schedule

06/04/18-6/24/18

(Times/Dates are anticipated, weather permitting)

No Construction Operations

July 4th Holiday Noon Tuesday, 07/03 – 0600 Thursday, 07/05

 

Asphalt Paving

  • 06/11 – Asphalt Pavement Haul & Operations will commence Monday, 06/11 and continue for approximately 5-6 weeks (weather permitting), Paving Ops will be running Dawn-to-Dusk once initiated.  Paving will begin in Ault and proceed to the south.

Hauling Operations

  • 06/04-06/24 - Haul of Embankment & Road Base will continue M-F (0600-1800 daily) primarily in the Eaton area at various sites in preparation of roadway for paving operations.

Concrete Placement

  • Concrete Sidewalk, Median Curb, ADA Ramps plus corner Curb & Gutter sections on the west side of US 85 will be in the process of being removed and replaced.
    • 06/04-06/24 - Curb & Gutter + ADA Ramps placement at corners will be underway at various locations through Eaton.
    • 06/04-06/08 - Town of Eaton Sidewalk Removal/Replacement should be complete (weather permitting) on/about Friday, 06/08. 

Trimming Full Depth Reclamation (FDR) Sections

  • 06/04-06/15 - Trimming of FDR Sections underway between Eaton-Ault project wide.

Concrete Pavement Removal

  • 06/04-06/15 – Removal of old concrete pavement and backfill of excavated areas, through Eaton.

Concrete Drainage Pipe & Inlets

  • 06/04-06/15– Placement of Concrete Drainage Pipe and Concrete Inlets near 2nd Str. in Eaton.

Bridge Rail

  •  7/14 – Guard Rail on Weld Canal bridge over US 85 anticipated to be completed.