Spring Street Project: UPDATES

After three-years in the planning and development phase, in an effort to improve mobility, safety and the appearance of the community; the Spring Street project has officially started. This will be the first of many communications from the Central City’s Public Works Department; that will serve as the 2019 Spring Street Construction Update. We will continue to use this form of communication [In addition to the City website] as the project continues, so as to better inform those Central City Business Community members potentially impacted by the project.

June 13:

Central City Public Works Department 2019 Spring Street Construction; Latest Update.  We will continue to use this form of communication [In addition to the City website] as the project continues, so as to better inform those Central City Business Community members potentially impacted by the project. 

As you are already aware, the 2019 Spring Street is under progress. The project area is on Spring Street from Gregory Street and continuing south along Spring Street to Roworth Street. This project includes burying the existing overhead utilities, replacing streetlights, replacing the existing sidewalks, curbs, gutters and performing a 2” mill and overlay of the roadway pavement. Avery Construction, Inc. will be performing the construction activities on behalf of the Central City.

Currently – Week of June 10th - our work efforts include:

  • Temporary ramp for emergency egress at the Easy Street Arcade
  • Installation of (2) new drains behind Scarlet’s and Easy Street
  • Installation of new curb and gutter behind Scarlet’s and Easy Street
  • Removal of the sidewalk, curb and gutter in front of 130 Spring Street

Week of June 17th:

  • Replace the sidewalk behind Scarlet’s and Easy Street
  • Continue sidewalk, curb and gutter removal in front of 114, 110 and 100 Spring Street (temporary walk in access will be provided)
  • Begin excavation for the undergrounding of utilities

 

June 3:

You may already be aware that construction along Spring Street has begun. The project area is from Spring and Gregory Streets and continuing south along Spring Street to Roworth Street. This project includes burying the existing overhead utilities, replacing streetlights, replacing the existing sidewalks, curbs, gutters and performing a 2” mill and overlay of the roadway pavement. Avery Construction, Inc. will be performing the construction activities on behalf of the Central City.

Currently work efforts include:

  • Removal of the sidewalk behind Scarlet’s and Easy Street
  • Temporary ramp for emergency egress at the Easy Street Arcade
  • Installation of (2) new drains behind Scarlet’s and Easy Street
  • Removal of the sidewalk, curb and gutter in front of 130 Spring Street
  • Continue sidewalk, curb and gutter removal as needed

Replace curb and gutter previously removed Week of June 17th:

  • Sidewalk replacement will begin (starting behind Easy Street and Scarlets)

Lane closures will occur, but the roadway will remain open during the project.

All dates are contingent on weather/site conditions and subject to change. Please contact 720-279- 7336 with any questions or concerns.